Evergreen Release Schedule and End of Life Policy
Evergreen time-based releases occur every six months with each major release getting 15 months of support (12 for general bugs and 3 more for security).
Releases are planned for (roughly) March and September since this works best for public libraries and at the same time gives academic/government institutions extra time to plan summer upgrades. This should also allow the community to expect a more predictable release cycle.
Below shows examples of how this schedule applies to the current Evergreen supported releases.
Release | General Release Date | End of Life (general bug fixes) | End of Life (security bug fixes) |
---|---|---|---|
3.12 | 2023-12-13 | 2024-12-13 | 2025-03-13 |
3.13 | 2024-06-07 | 2025-06-07 | 2025-09-07 |
3.14 | 2024-10-23 | 2025-10-23 | 2026-01-23 |
3.15 | 2025-04-16 | 2026-04-16 | 2026-07-16 |
Point Release Schedule
The Evergreen developer community plans bug-fix point releases on the third Wednesday of every month. There may be exceptions to this schedule, for example, when a critical bug requires more immediacy in the next point release or when there aren't a sufficient number of bug fixes to warrant a new release.